Legacy Service Connection Characteristics
|
|
|
Required Governance Actions
|
|
|
Pre demolition gas pathways with unknown pressurization, undocumented branch lines, aging valves, corrosion, shared feeds between structures.
|
High energy ignition and explosion risk; hidden branch lines; incomplete shutdowns; residual gas in abandoned lines.
|
Shapes method envelope; restricts mechanical operations; requires evidence based verification; cannot rely on verbal shutdown assurances.
|
Identify → Verify isolation → Purge → Pressure test → Document → Monitor
|
|
|
Legacy domestic, fire, irrigation, or process water systems with undocumented tie-ins, shared mains, abandoned but charged lines, underground routing not shown on plans.
|
Pressurized discharge; slab undermining; soil washout; biological hazards; unexpected activation of fire systems.
|
Influences collapse behavior; affects environmental stability; impacts sequencing and access; requires structural caution.
|
Locate → Pressure test → Isolate → Drain → Document → Monitor
|
|
|
Pre demolition electrical systems with abandoned but energized circuits, mislabeled panels, shared feeds, temporary power, underground conduits not documented.
|
Electrocution; arc flash; energized abandoned circuits; equipment damage; lethal invisible hazards.
|
Treated as energized until proven otherwise; shapes equipment selection; requires strict lockout/tagout; high consequence verification.
|
Trace → Test → De-energize → Lockout/Tagout → Document → Monitor
|
|
|
Legacy fiber, copper, coax, data, and security lines crossing properties, serving multiple tenants, sharing conduits with power, remaining active despite canceled accounts.
|
Legal liability; operational disruption; shared conduit hazards; accidental service interruption to critical facilities.
|
Influences neighbor impact; affects sequencing; requires coordinated shutdown; prevents unintended service outages.
|
Identify → Coordinate shutdown → Verify → Protect → Document → Monitor
|